ESH were contracted to design and supply materials and labour to install multiple ramp trace heating systems, utilising self regulating heating tape to prevent snow settlement and ice formation on the hospitals multi storey car park.
To achieve this a loading of 180 watts per m² was required, by using heating tape rated at 30 w/m set to 150-200mm spacing, this gave us an installed length of 6m of heating tape per m² of ramp floor area.
In total over 1500 metres of type FBT self regulating heating tape was installed throughout this project.